Blackwell secure North Renfrewshire Scheme

Blackwell have been awarded Phase 1 of the North Renfrewshire Flood Prevention Scheme adjacent to the south bank of the River Clyde. We mobilised to site in Renfrew at the beginning of August and are progressing with the following elements of the scheme:
  • earthworks to form four flood embankments
  • toe drainage alongside the embankments and connections to existing systems
  • four reinforced retaining walls at the embankment ends
  • two sheet piled and concrete lined bypass chambers
  • 1600mm diameter interconnecting pipes

 